top of page

Mission Critical

IBM Utility Distribution Replacement
Westchester County, New York
 

​Owner/Developer: IBM Corporation

 

Project Team

Structural: Thune Associates, PC

Mechanical/Electrical: Jaros Baum & Bolles

Tunnel: Jenny Engineering Corporation

Landscape: Imbiano-Quigley Landscape Architects, PC

Construction Manager: Structure Tone, Inc.

 

Program and Design:  Replaced existing underground utilities with a new, nine foot diameter underground utility tunnel. Using a Tunnel Boring Machine the utility tunnel was installed 40 feet below grade. This design approach minimized environmental disturbance and maintained uninterrupted utility services to existing buildings. Daily operations and traffic circulation were also undisturbed during construction. The tunnel is 2,000 feet long and provides for convenient installation of future utilities and technologies.

Photography: Bob Vergara

Mission Critical Project
New York

Owner: Withheld

 

Project Team

Structural: McLaren Engineering Group

Mechanical/Electrical/Plumbing: EYP Mission Critical Facilities

General Contractor: Pavarini Construction Co.

 

Program and Design:  To support large Data Center operations, new free-standing hardened sub-station building was constructed on the site with dual 4,000-amp services each from a separate utility company feeder. An addition to the building was designed to accommodate four 1,000 kw emergency generators with paralleling gear. Four 750 KVA UPS systems were designed, each in an isolated room, to achieve an N+2 design. A Data Center cooling system was provided with high-density rack-mounted cooling units.

Data Center
Connecticut
 

​Client: Confidential

 

Project Team

Mechanical/Electrical/Plumbing: Edwards & Zuck, DPC

Information/Technology: Lilker Associates

Construction Manager: Pavarini Construction Co.

 

Program and Design:  To support a 200-person trading floor for a large financial services firm a new N+2 Data Center was designed with redundant electrical utility service with main-tie-main configuration, UPS system, emergency generators with paralleling gear, critical room air conditioning system, and clean agent and pre-action fire protection system. Design services included strategic planning of mission critical facilities, coordination of Architectural, MEP, and technology design, design of cabling infrastructure, full Data Center and short circuit and arc-flash evaluation, Factory acceptance testing, and full commissioning.

bottom of page