One DeKalb Construction Progressing

January 16, 2018

 

 

Wall panels are being set and floor structure is being erected at 1 DeKalb Avenue in White Plains.  For walls above the second floor, this project was designed with Panelized Light Gauge Metal Framing fabricated, off-site, by Duraframe Solutions in in Webster, New York.  The panels arrive pre-sheathed with an air and moisture barrier and are lifted in place with a crane.  All the exterior, corridor, and shear walls are panelized; interior non-load bearing walls will be constructed on-site.  The 77-unit multi-family building is on schedule for completion in before the end of year.